Tanzania
Evaluation of Peace Corps/Tanzania
Report Information
Recommendations
Disclaimer: Open/Closed recommendations are updated semiannually.That the country director ensures there are sufficient funds at the post available to improve housing when communities are unable to pay for necessary upgrades.
That the director for programming provide sufficient oversight to ensure that the process of site development is well-planned and organized and staff are appropriately documenting and sharing information about the progress of each site.
That the director for programming revise the timeline for site development to conform with the Programming, Training, and Evaluation Guidance that the site identification process should begin a year before Volunteers arrive at site.
That the country director ensure that site and housing criteria checklists are accurately completed and approved before Volunteers move into their permanent sites.
That the country director develop and implement a post site history file standard operating procedure which conforms with the requirements of Safety and Security Instruction 401.